Step 12 – Post Cutover Delta Sync

This step in the project is essentially the same as #9 – Pre-Cutover Delta Sync

Either the use of the consistency report and delta syncs for specific folders should be made or a delta sync of the entire hierarchy should be performed.  The former option may equate to an overall shorter duration than processing the entire hierarchy, especially if 90% or more of the hierarchy is unchanged.